Today had the Frame Walk. It was a smooth one and the builder was helpful in every way to accommodate the needs.

You get to check if the wiring and connections are in the place you ordered. Anything unusual you can point out.

I had insulation not completed so discussed about that. Was told that if the insulation not done as it should be, it will not pass the test and approval.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Tue May 27, 2014 6:16 pm 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
Glad it went well for you. How far before closing that you get the frame walk ? We are in phase 3 and closing September 23rd.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Wed May 28, 2014 4:19 pm 
Offline

Joined: Wed Feb 26, 2014 1:14 pm
Posts: 686
Location: Phase 3A
I got it two months before closing it. I would assume for you it would be in July.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Thu May 29, 2014 10:57 am 
Offline

Joined: Wed Jan 29, 2014 11:52 am
Posts: 247
did you ask if you could run extra wires, add insulation into the walls, or put screws into the floor yourself?

They will make the house to the OBC, but that really is a minimum.

_________________
Image
Renfrew - Phase 3


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Thu May 29, 2014 2:36 pm 
Offline

Joined: Wed Apr 23, 2014 10:52 am
Posts: 781
Carl wrote:
Was told that if the insulation not done as it should be, it will not pass the test and approval.


Its good they send an inspector to make sure it is all correct before the wall guy shows up.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Thu May 29, 2014 3:12 pm 
Offline

Joined: Wed Feb 26, 2014 1:14 pm
Posts: 686
Location: Phase 3A
I did not ask if I could run extra wires, add insulation into the walls, or put screws into the floor.

I was more concerned about the insulation as I found many places it was not up to the mark and the Frame work guy mentioned that it will be taken care of. I will check again to make sure it is done.

You could do the wires before the drywall is up as long as you do not mess around too much. The best time to do is just after the frame walk. These site guys so so much better than ladies over the design centre.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Sun Jun 01, 2014 7:43 am 
Offline

Joined: Fri Jan 24, 2014 7:59 pm
Posts: 178
Location: Phase 3 Hawthorn North -Trenton Elevation G
Someone was coming in the day of our framewalk to put the screws in. Awesome experience


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Sun Jun 01, 2014 8:07 am 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
ShazadMirza wrote:
Someone was coming in the day of our framewalk to put the screws in. Awesome experience


Screws for what ? Wasn't there screws before ?


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Sun Jun 01, 2014 9:31 am 
Offline

Joined: Sun Feb 02, 2014 4:06 pm
Posts: 313
I was thinking of asking the coordinator to ask the construction team to have the floors screwed down before my frame walk.

Sharzad
Can you confirmed that Mattamy will screws the floors down - I thought it was nail and glue?

_________________
Image
Hawthorne Village North - Phase 3A
Lucan Corner Elevation "D"
Closing August 2014


Last edited by SnS86 on Tue Jun 03, 2014 11:59 am, edited 2 times in total.

Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Tue Jun 03, 2014 4:18 am 
Offline

Joined: Fri Jan 24, 2014 7:59 pm
Posts: 178
Location: Phase 3 Hawthorn North -Trenton Elevation G
Email Tony, he assured me that the screws would be in


Last edited by ShazadMirza on Wed Jun 11, 2014 8:36 pm, edited 1 time in total.

Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Tue Jun 03, 2014 7:53 am 
Offline

Joined: Wed Apr 23, 2014 10:52 am
Posts: 781
ShazadMirza wrote:
SnS86 wrote:
I was thinking of going in and screwing the floor down before my frame walk.

Sharzad
Can you confirmed that Mattamy will screws the floors down - I thought it was nail and glue?

Email Tony, he assured me that the screws would be in


You should get that in writing. Theres plenty of complaints on this website about people saying they were told this or that and it didn't get done. If hes being honest with you, he'll have no problem doing it in writing.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Tue Jun 03, 2014 9:13 am 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
Can some one plz explain why we need to nail down the floor ? Isn't it a standard process to glue and nail down the floor? Mattamy should be doing this.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Tue Jun 03, 2014 9:16 am 
Offline

Joined: Wed Apr 23, 2014 10:52 am
Posts: 781
Aaa wrote:
Can some one plz explain why we need to nail down the floor ? Isn't it a standard process to glue and nail down the floor? Mattamy should be doing this.


Probably has something to do with squeaky floors.


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Tue Jun 03, 2014 9:31 am 
Offline

Joined: Fri Mar 07, 2014 12:54 pm
Posts: 37
How early before your Frame Walk Appointment did they call you?

--Kyra

_________________
Hawthorne Village North - Phase 3
Normandale - Elevation "D"
Closing July 2014


Top
 Profile  
Reply with quote  
 Post subject: Re: Frame Walk
PostPosted: Tue Jun 03, 2014 3:15 pm 
Offline

Joined: Wed Feb 26, 2014 1:14 pm
Posts: 686
Location: Phase 3A
approximately 2 months before your closing.


Top
 Profile  
Reply with quote  
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 43 posts ]  Go to page 1, 2, 3  Next

All times are UTC - 5 hours


Who is online

Users browsing this forum: No registered users and 4 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron
Powered by phpBB® Forum Software © phpBB Group
[ Time : 0.012s | 13 Queries | GZIP : Off ]