PostPosted: Wed Jun 04, 2014 10:17 am 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
Hello,

So for those of us that are closing in September - coming week would be the week to watch :)

If no call or email then we should be clear of any delays ;)

Good luck to all of us closing in September .


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 04, 2014 11:12 am 
Offline

Joined: Wed Feb 26, 2014 1:14 pm
Posts: 686
Location: Phase 3A
Aaa wrote:
Hello,

So for those of us that are closing in September - coming week would be the week to watch :)

If no call or email then we should be clear of any delays ;)

Good luck to all of us closing in September .


Do not expect any closing delays for September closing as you were not the first to close. Only those who were July closings got delayed and that was also only a handful ones.


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 04, 2014 11:14 am 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
Carl wrote:
Aaa wrote:
Hello,

So for those of us that are closing in September - coming week would be the week to watch :)

If no call or email then we should be clear of any delays ;)

Good luck to all of us closing in September .


Do not expect any closing delays for September closing as you were not the first to close. Only those who were July closings got delayed and that was also only a handful ones.


Awesome. But last week i went to the site any there is hardly any progress except the foundation poured. Will they finish the house in 110 days ? Hopefully if they work day and night lol


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 04, 2014 11:34 am 
Offline

Joined: Fri Feb 14, 2014 5:08 pm
Posts: 71
you would be surprised.. they work really fast.. my closing is in end of august and literally every weekend when I go to check up on the progress, they have completed a lot more than I expected them to do.. my townhouse is even started to be bricked now so they are moving fairly fast..


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 04, 2014 11:39 am 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
awais wrote:
you would be surprised.. they work really fast.. my closing is in end of august and literally every weekend when I go to check up on the progress, they have completed a lot more than I expected them to do.. my townhouse is even started to be bricked now so they are moving fairly fast..


hi WAIS,
Hopefully they start work on our lot - work fast but hopefully do a quality job.


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 04, 2014 12:40 pm 
Offline

Joined: Mon Feb 10, 2014 6:48 pm
Posts: 10
I have a friend that works at construction at Mattamy and supposedly they can bring up a home in 90 days. Pretty quick!


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 04, 2014 12:58 pm 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
gnsahana wrote:
I have a friend that works at construction at Mattamy and supposedly they can bring up a home in 90 days. Pretty quick!


Regardless of the size of the house ? Hopefully quality over quantity when it comes to building houses.


Top
 Profile  
Reply with quote  
PostPosted: Wed Jun 04, 2014 1:15 pm 
Offline

Joined: Wed Feb 26, 2014 1:14 pm
Posts: 686
Location: Phase 3A
Aaa wrote:
Carl wrote:
Aaa wrote:
Hello,

So for those of us that are closing in September - coming week would be the week to watch :)

If no call or email then we should be clear of any delays ;)

Good luck to all of us closing in September .


Do not expect any closing delays for September closing as you were not the first to close. Only those who were July closings got delayed and that was also only a handful ones.


Awesome. But last week i went to the site any there is hardly any progress except the foundation poured. Will they finish the house in 110 days ? Hopefully if they work day and night lol


For example as to when they start pouring the foundation to a complete product, for July closing they started pouring in April. It is about 3 months they complete everything.

I am certain about the quality, because most of the work is done by external sub contractors.


Top
 Profile  
Reply with quote  
PostPosted: Thu Jun 05, 2014 7:17 pm 
Offline

Joined: Wed Feb 19, 2014 3:25 pm
Posts: 101
Can the builder push closing out further once they have confirmed closing as per agreement? And are they supposed to confirm closing 90 days prior or is it 120 days?


Top
 Profile  
Reply with quote  
PostPosted: Fri Jun 06, 2014 9:34 am 
Offline

Joined: Wed Jan 29, 2014 11:52 am
Posts: 247
It is 90 days prior. The exact date is on your Tarion form.

They technically can push it out further. However it has to be either mutually agreed, or else Mattamy will have to pay a daily penalty rate.

_________________
Image
Renfrew - Phase 3


Top
 Profile  
Reply with quote  
PostPosted: Sun Jun 08, 2014 10:10 am 
Offline

Joined: Mon Sep 02, 2013 9:53 pm
Posts: 63
Mine got delayed, I was Sept 9 now its Oct 9th.

_________________
HV North - Phase 3
Renfrew - Elevation C
Closed Oct 2014


Top
 Profile  
Reply with quote  
PostPosted: Sun Jun 08, 2014 10:17 am 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
endiz wrote:
Mine got delayed, I was Sept 9 now its Oct 9th.


Oh no :(

What lot were u at ? Our closing is September 23rd and we hope its not delayed .


Top
 Profile  
Reply with quote  
PostPosted: Sun Jun 08, 2014 5:31 pm 
Offline

Joined: Wed Feb 19, 2014 3:25 pm
Posts: 101
Endiz, is that a firm oct 9 closing or can they change it again?
We are closing oct 1 and not s ure if this is a domino effect


Top
 Profile  
Reply with quote  
PostPosted: Sun Jun 08, 2014 5:40 pm 
Offline

Joined: Mon Jan 27, 2014 10:13 pm
Posts: 294
bd10 wrote:
Endiz, is that a firm oct 9 closing or can they change it again?
We are closing oct 1 and not s ure if this is a domino effect


That's what I was thinking too. Based on the progress it seems there will be more delays. They havent start framing our lot and its suppose to be due in 105 days.


Top
 Profile  
Reply with quote  
PostPosted: Mon Jun 09, 2014 11:10 am 
Offline

Joined: Tue Oct 23, 2007 3:32 pm
Posts: 150
Sooooo, just got official notification that my September 25th closing date has been delayed until October 30th.

This is lot 110 on Tough Gate in HVP3. I'm "guessing" this will be the case for all of the houses on the south side of Tough Gate.


Top
 Profile  
Reply with quote  
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 23 posts ]  Go to page 1, 2  Next

All times are UTC - 5 hours


Who is online

Users browsing this forum: No registered users and 6 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum