 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Nov 15, 2016 9:57 am 
Offline

Joined: Mon Nov 14, 2016 8:19 am
Posts: 14
Location: Milton, Ontario
ajd wrote:
HanselMugatu wrote:
Just got our delay notification today :-( ...original close was Feb 15, pushed to March 15.

Did they say what is causing the delay?


What I have usually seen from the past as this time there is no strike. Its usually the land development process that causes the delay which they usually mention in their email.

_________________
Amer Sheikh
Sales Representative
Right At Home Realty Inc., Brokerage
Cell: 647-787-0000


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Nov 15, 2016 11:04 am 
Offline

Joined: Mon Jan 25, 2016 9:38 am
Posts: 88
They said "This is due to some trade shortages we are experiencing on site at this time."

Sounds like bad planning to me.


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Nov 15, 2016 11:06 am 
Offline

Joined: Sun Nov 08, 2015 9:21 pm
Posts: 51
HanselMugatu wrote:
They said "This is due to some trade shortages we are experiencing on site at this time."

Sounds like bad planning to me.


So is the new closing date a firm closing date?

_________________
Hawthorne South Village | Phase 6
Underwood Model | French Chateau Elevation

Current closing May 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Nov 15, 2016 11:52 am 
Offline

Joined: Mon Jan 25, 2016 9:38 am
Posts: 88
It's not firm yet, it's tentative.


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Nov 15, 2016 2:19 pm 
Offline

Joined: Mon Nov 14, 2016 8:19 am
Posts: 14
Location: Milton, Ontario
HanselMugatu wrote:
It's not firm yet, it's tentative.


They only firm it 90 days before closing. If they are on time after the one month delay. Next month 14th you should most likely get a firm closing date.

_________________
Amer Sheikh
Sales Representative
Right At Home Realty Inc., Brokerage
Cell: 647-787-0000


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Thu Nov 24, 2016 6:54 pm 
Offline

Joined: Sun Jan 31, 2016 9:26 pm
Posts: 25
pong35 wrote:
Hi Lalexa, we were hoping a closing date same as yours, :D . It's just because we would like our son to finish his school first before moving to Milton.


In case you weren't at Mattamy University a couple weeks ago, Whitney mentioned that we can request to push our closing dates a little bit. Just e-mail her and see if she can work something out for you.


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Nov 29, 2016 11:04 am 
Offline

Joined: Mon Oct 26, 2015 9:49 am
Posts: 117
Found possible house numbers.

http://maps.milton.ca/MGIS/WebPages/Map ... iewer.aspx

Zoom in and the numbers will show.

Also, I found this, its only updated upto Oct, 2016. Satellite picture of the site.

https://www.terraserver.com/view?utf8=% ... x=&center=

_________________
Hawthorne South Village - Phase 6
Midland Corner - Craftsman Elevation
Leger way
Delayed Closing date April 18, 2017
Moved in date May 18, 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Nov 29, 2016 11:06 am 
Offline

Joined: Mon Oct 26, 2015 9:49 am
Posts: 117
treblave wrote:
pong35 wrote:
Hi Lalexa, we were hoping a closing date same as yours, :D . It's just because we would like our son to finish his school first before moving to Milton.


In case you weren't at Mattamy University a couple weeks ago, Whitney mentioned that we can request to push our closing dates a little bit. Just e-mail her and see if she can work something out for you.


Confirmed, Whitney informed us about this too.

_________________
Hawthorne South Village - Phase 6
Midland Corner - Craftsman Elevation
Leger way
Delayed Closing date April 18, 2017
Moved in date May 18, 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Wed Nov 30, 2016 12:24 pm 
Offline
User avatar

Joined: Sun Jan 26, 2014 11:48 pm
Posts: 217
Location: Milton
pong35 wrote:
treblave wrote:
pong35 wrote:
Hi Lalexa, we were hoping a closing date same as yours, :D . It's just because we would like our son to finish his school first before moving to Milton.


In case you weren't at Mattamy University a couple weeks ago, Whitney mentioned that we can request to push our closing dates a little bit. Just e-mail her and see if she can work something out for you.


Confirmed, Whitney informed us about this too.


pong35 - were you able to move your closing?

_________________
Lauren and Eric
Hawthorne South Village | Phase 6

Firm Closing Date: September 14, 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Wed Nov 30, 2016 1:52 pm 
Offline

Joined: Mon Oct 26, 2015 9:49 am
Posts: 117
Quote:
Confirmed, Whitney informed us about this too.


Quote:
pong35 - were you able to move your closing?


Not yet, but if we have a firm closing on April we will do it. I will paste what Whitney told us.

"At times, Mattamy does allow mutual extensions to occur. This has to go through several approvals prior to an amendment being drafted and we typically can only offer two weeks or until the end of the month. This becomes extremely hard to move closings in March, April, May and June as the builders are typically at their maximum capacity of closings per day.

If you do not receive a notification on or before January 18th, 2017 then you can assume your closing has become firm. You are more than welcome to reach out to me on the 19th requesting an extension if your date becomes firm."

_________________
Hawthorne South Village - Phase 6
Midland Corner - Craftsman Elevation
Leger way
Delayed Closing date April 18, 2017
Moved in date May 18, 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Wed Dec 14, 2016 10:12 pm 
Offline

Joined: Mon Feb 22, 2016 9:53 pm
Posts: 59
Nunu wrote:
Our Closing is in Feb As well ....I guess Hansel and I would be the first to move in the area....our lot is 171...close to you guys.
MI175 wrote:
HanselMugatu wrote:
Yes, we are 174 I think.


We'll be sharing a fence!

MI175 wrote:
HanselMugatu wrote:
Yes, we are 174 I think.


We'll be sharing a fence!

D


Hi,

Do you have an idea how much is the fence?

Thanks


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Mon Jan 16, 2017 9:25 pm 
Offline
User avatar

Joined: Sun Jan 26, 2014 11:48 pm
Posts: 217
Location: Milton
pong35 wrote:
Quote:
Confirmed, Whitney informed us about this too.


Quote:
pong35 - were you able to move your closing?


Not yet, but if we have a firm closing on April we will do it. I will paste what Whitney told us.

"At times, Mattamy does allow mutual extensions to occur. This has to go through several approvals prior to an amendment being drafted and we typically can only offer two weeks or until the end of the month. This becomes extremely hard to move closings in March, April, May and June as the builders are typically at their maximum capacity of closings per day.

If you do not receive a notification on or before January 18th, 2017 then you can assume your closing has become firm. You are more than welcome to reach out to me on the 19th requesting an extension if your date becomes firm."


pong35 - Noticed the closing date in your signature changed from April to May. Were you informed of a delay? or is it only because you asked for it to be delayed? Trying to figure out if we'll be delayed or not, but we won't find out for sure until April!

_________________
Lauren and Eric
Hawthorne South Village | Phase 6

Firm Closing Date: September 14, 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Mon Jan 16, 2017 9:44 pm 
Offline

Joined: Mon Oct 26, 2015 9:49 am
Posts: 117
lalexa wrote:

pong35 - Noticed the closing date in your signature changed from April to May. Were you informed of a delay? or is it only because you asked for it to be delayed? Trying to figure out if we'll be delayed or not, but we won't find out for sure until April!


Hi lalexa,

We were just informed just this morning (January 16, 2017) of the delay. And we were told to request for an extension when
the firm date is already given.

I guess you also read that someone was delayed from May 2017 to August 2017?

We had our Mattamy University last January 5 and were told that because of Labour and material shortage there will be delay for some.

_________________
Hawthorne South Village - Phase 6
Midland Corner - Craftsman Elevation
Leger way
Delayed Closing date April 18, 2017
Moved in date May 18, 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Mon Jan 16, 2017 11:38 pm 
Offline
User avatar

Joined: Sun Jan 26, 2014 11:48 pm
Posts: 217
Location: Milton
pong35 wrote:
lalexa wrote:

pong35 - Noticed the closing date in your signature changed from April to May. Were you informed of a delay? or is it only because you asked for it to be delayed? Trying to figure out if we'll be delayed or not, but we won't find out for sure until April!


Hi lalexa,

We were just informed just this morning (January 16, 2017) of the delay. And we were told to request for an extension when
the firm date is already given.

I guess you also read that someone was delayed from May 2017 to August 2017?

We had our Mattamy University last January 5 and were told that because of Labour and material shortage there will be delay for some.


Yes! that's where I saw your new signature :) Interesting! Thanks for confirming. We haven't had our Mattamy University session yet.

_________________
Lauren and Eric
Hawthorne South Village | Phase 6

Firm Closing Date: September 14, 2017


Top
 Profile  
Reply with quote  
 Post subject: Re: Phase 6 - Leger Way
PostPosted: Tue Jan 17, 2017 8:54 am 
Offline

Joined: Mon Oct 26, 2015 9:49 am
Posts: 117
lalexa wrote:

Yes! that's where I saw your new signature :) Interesting! Thanks for confirming. We haven't had our Mattamy University session yet.


With the Mattamy University info and the 3 months delay that we read from other home owners, I feel that they are concentrating their labour to one site to offset the labour shortage, thus leaving some site for a while. My opinion only.

_________________
Hawthorne South Village - Phase 6
Midland Corner - Craftsman Elevation
Leger way
Delayed Closing date April 18, 2017
Moved in date May 18, 2017


Top
 Profile  
Reply with quote  
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 204 posts ]  Go to page Previous  1 ... 7, 8, 9, 10, 11, 12, 13, 14  Next

All times are UTC - 5 hours


Who is online

Users browsing this forum: No registered users and 8 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Group
[ Time : 0.013s | 13 Queries | GZIP : Off ]