Author:  Milton1 [ Thu Jan 26, 2017 1:37 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Ours is the first notice.

Author:  Alexjoaquin [ Mon Jan 30, 2017 10:02 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

pong35 wrote:
Alexjoaquin wrote:
Milton1 wrote:
Hi

The dreaded email came in this morning:) the date has been moved to August 2017. 1st tentative was April 2017. Anyone else got the delay email.



Got ours today!


@Alexjoaquin, is it the same? Your new tentative closing is August 2017?


Yes! August 15 to be exact

Author:  Bravo [ Tue Jan 31, 2017 4:19 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

We received an email today and our new tentative closing date is August 22, 2017.

Author:  Gjeny [ Tue Jan 31, 2017 8:01 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Received ours too today, new tentative closing date is August 23!

Author:  bobbymann [ Tue Feb 14, 2017 3:53 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Any one else booked on Farmstead - closing Aug 2018 ? Phase 8 a?

Author:  chocholate [ Tue Feb 14, 2017 10:44 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

we have booked Pelham (EM) closing in April 2018. Phase 8 on Farmstead

Author:  bobbymann [ Wed Feb 15, 2017 1:54 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

I have a Pelham model, lookout basement with side door. Will be putting up for sale soon.
I need to move to Manitoulin Island.

Author:  chocholate [ Wed Feb 15, 2017 8:04 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Is it possible? I heard you cannot sell before possession

Author:  Bravo [ Fri Apr 14, 2017 10:55 am ]
Post subject:  Re: Clifford Point - HSV - Phase 6

I received an email yesterday stating that they have completed the roofing of the house and now they are going to commence work on the interior of the house. Does anyone have an idea if all interior work will take up to August 22 which is the new tentative closing date? or is there a possibility that they can close earlier than that date?

Author:  funnyman82 [ Fri Apr 14, 2017 1:43 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

If they have already given notice that you are delayed till August, they will not close earlier than that. I inquired about that on my home last year as well.

Author:  'Da_Belletruttis [ Sun Apr 16, 2017 4:56 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Bravo wrote:
I received an email yesterday stating that they have completed the roofing of the house and now they are going to commence work on the interior of the house. Does anyone have an idea if all interior work will take up to August 22 which is the new tentative closing date? or is there a possibility that they can close earlier than that date?


You will be fine. More than enough time for them to complete by Aug 22 if they are at the roof now. Barring a significant bricklayer delay, you will likely hit your current Aug 22nd date.

Author:  Bravo [ Mon Apr 24, 2017 2:22 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

'Da_Belletruttis wrote:
Bravo wrote:
I received an email yesterday stating that they have completed the roofing of the house and now they are going to commence work on the interior of the house. Does anyone have an idea if all interior work will take up to August 22 which is the new tentative closing date? or is there a possibility that they can close earlier than that date?


You will be fine. More than enough time for them to complete by Aug 22 if they are at the roof now. Barring a significant bricklayer delay, you will likely hit your current Aug 22nd date.



Thanks for the inputs. Have you all signed up for the AC group buy? Is there a place that I need to sign up? Please let me know. Thanks.

Author:  lalexa [ Mon Apr 24, 2017 3:22 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Bravo wrote:
I received an email yesterday stating that they have completed the roofing of the house and now they are going to commence work on the interior of the house. Does anyone have an idea if all interior work will take up to August 22 which is the new tentative closing date? or is there a possibility that they can close earlier than that date?



We are closing 2 days after you, and they haven't even started our framing yet! We've had just foundation for 6 months. I have a feeling we're in for a third delay, but I'm keeping watch on the construction site. If they start framing by the end of the month, I will have hope again lol.

I think you will be on time though, they can build an entire house in 4 months, and sounds like yours is half way done :)

Author:  Bravo [ Fri Apr 28, 2017 10:31 am ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Has anyone signed up for the AC group buy yet? Please let me know where you all are signing up.

btw, I was contacted today for a frame walk of the house for early next week.

Author:  Milton1 [ Fri Apr 28, 2017 8:50 pm ]
Post subject:  Re: Clifford Point - HSV - Phase 6

Completed our frame walk last week, looks like August dates will be good, fingers crossed. Lots 324 & 325 have been completed new owners have moved in.